Abstract
Cost overrun and delay are very frequent phenomenon and are generally associated with nearly all projects in the world especially in developing countries. Generally, 71 percent of projects suffer from cost/time overrun in the world with an average cost overrun of 43%. In this study, 25 factors causing cost and time overrun were considered. The ranking of 25 factors causing cost overrun and delay in construction projects made on the basis of mean value of impact which was determined from 65 project data file and 65 executive’s opinion on structured instrument, giving equal weightage to both the values. The factor of “Inconsistent Cash Flow” was the most significant factor with impact value of 7.78 in severe category and “Weather Severity” was the least significant factor with impact value of 3.40 in moderate category. In this study, 65 projects of different departments executed by Frontier Works Organization (FWO) were considered which include 48 completed and 17 running projects. FWO is one of the biggest construction organizations of Pakistan with a financial worth of Rs.36 billions and annual turnover of Rs.22 Billions working all over Pakistan and abroad. Out of 65 selected projects, 38 were roads projects, 12 infrastructure and development projects (private sector) and 15 projects of Government Departments (Railway, WAPDA, Structures, Irrigation/ Power, Airports &Telecomm). Out of 65 projects, only 7 projects were completed within budget thus showing that 90 % projects are suffering from cost variation including 74% projects over running cost and 15% projects under running cost due to scope reduction. Only 2 projects were completed on planned schedule thus showing that 97% of projects were suffering from delay. Overall average cost overrun was 28.27% with an average delay of 2.1 years per project. The highest cost overrun has been observed in projects of Government Departments i.e. 37.59% and highest delay per projects was observed in roads projects i.e. 2.3 years per project. The public/private organizations, regulatory bodies, financing institutions and government should control the financing, planning, management and technical aspects of projects to minimize the cost/time overrun.
More Information
Status: | Published |
---|---|
Refereed: | Yes |
Depositing User (symplectic) | Deposited by Nadir, Hafiz |
Date Deposited: | 26 Jan 2023 15:16 |
Last Modified: | 12 Jul 2024 07:14 |
Item Type: | Article |